Hershey Chocolate Corporation

 

Hershey Chocolate Corporation was the first company that produced milk chocolate in America. With the passage to time, it focused only on chocolate production, and manufactured many innovative products. After the Second World War, it managed to export its products to 90 countries. In2006, its sales reached 5 billion dollars, and employed over 14,300 people.  

 

The objective of the project is to deploy an ERP system covering sales and procurement process. The following is the required schedule of the event.  

 

 

 

Activity 

Duration- Weeks 

Immediate Predecessors 

A–Select consultant for selecting system 

_____________ 

B–Meet with consultant to discuss ERP 

C–Meet with Board of Directors to explain proposal 

D–Develop request for proposals to give to vendors 

B,C 

E–Obtain vendor proposals 

F–Develop organization business cases including training 

G–Present business cases to Board of Directors 

H–Redo estimates in light of board requests for changes 

I–Initiate installation project 

 

 

 

  • Mention which approach should be used to execute this project and why? 
  • Out of the three phases, which phase/ phases can you identify from given scenario? 
  • Write the scope of this project in two lines. 
  • Use CPM to identify the critical path and the length of this project.  Also provide table to mention slack of each activity. 

Hershey Chocolate Corporation

Hershey Chocolate Corporation was the first company that produced milk chocolate in America. With the passage to time, it focused only on chocolate production, and manufactured many innovative products. After the Second World War, it managed to export its products to 90 countries. In2006, its sales reached 5 billion dollars, and employed over 14,300 people.

 

The objective of the project is to deploy an ERP system covering sales and procurement process. The following is the required schedule of the event. (Marks-10)

 

 

 

Activity

Duration- Weeks

Immediate Predecessors

A–Select consultant for selecting system

2

_____________

B–Meet with consultant to discuss ERP

4

A

C–Meet with Board of Directors to explain proposal

1

A

D–Develop request for proposals to give to vendors

3

B,C

E–Obtain vendor proposals

4

D

F–Develop organization business cases including training

8

E

G–Present business cases to Board of Directors

1

F

H–Redo estimates in light of board requests for changes

3

G

I–Initiate installation project

1

H

 

 

 

  • Mention which approach should be used to execute this project and why?
  • Out of the three phases, which phase/ phases can you identify from given scenario?
  • Write the scope of this project in two lines.
  • Use CPM to identify the critical path and the length of this project. Also provide table to mention slack of each activity.

Hershey Chocolate Corporation

Question-2- Hershey Chocolate Corporation was the first company that produced milk chocolate in America. With the passage to time, it focused only on chocolate production, and manufactured many innovative products. After the Second World War, it managed to export its products to 90 countries. In2006, its sales reached 5 billion dollars, and employed over 14,300 people.

The objective of the project is to deploy an ERP system covering sales and procurement process. The following is the required schedule of the event.

Activity
Duration- Weeks
Immediate Predecessors

A–Select consultant for selecting system
2
_____________

B–Meet with consultant to discuss ERP
4
A

C–Meet with Board of Directors to explain proposal
1
A

D–Develop request for proposals to give to vendors
3
B,C

E–Obtain vendor proposals
4
D

F–Develop organization business cases including training
8
E

G–Present business cases to Board of Directors
1
F

H–Redo estimates in light of board requests for changes
3
G

I–Initiate installation project
1
H

 

Mention which approach should be used to execute this project and why?
Out of the three phases, which phase/ phases can you identify from given scenario?
Write the scope of this project in two lines.
Use CPM to identify the critical path and the length of this project. Also provide table to mention slack of each activity.

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more